July
30, 2006
Audit Finds U.S. Hid Actual
Cost of Iraq Projects
By
JAMES GLANZ
BAGHDAD, Iraq, July 29 — The
State Department agency in charge of $1.4 billion in reconstruction money in
Iraq used an accounting shell game to hide ballooning cost overruns on its
projects there and knowingly withheld information on schedule delays from
Congress, a federal audit released late Friday has found.
The agency hid
construction overruns by listing them as overhead or administrative costs,
according to the audit, written by the Special Inspector General for Iraq
Reconstruction, an independent office that reports to Congress, the Pentagon
and the State Department.
Called the
United States Agency for International Development, or A.I.D., the agency
administers foreign aid projects around the world. It has been working in Iraq
on reconstruction since shortly after the 2003 invasion.
The report by
the inspector general’s office does not give a full accounting of all
projects financed by the agency’s $1.4 billion budget, but cites several
examples.
The findings
appeared in an audit of a children’s hospital in Basra, but they referred
to the wider reconstruction activities of the development agency in Iraq.
American and Iraqi officials reported this week that the State Department
planned to drop Bechtel, its contractor on that project, as signs of budget and
scheduling problems began to surface.
The United
States Embassy in Baghdad referred questions to the State Department in
Washington, which declined to comment immediately.
In March 2005,
A.I.D. asked the Iraq Reconstruction and Management Office at the United States
Embassy in Baghdad for permission to downsize some projects to ease widespread
financing problems. In its request, it said that it had to “to absorb
greatly increased construction costs” at the Basra hospital, and that it
would make a modest shift of priorities and reduce “contractor
overhead” on the project.
The embassy
office approved the request. But the audit found that the agency interpreted
the document as permission to change reporting of costs across its program.
Referring to
the embassy office’s approval, the inspector general wrote, “The
memorandum was not intended to give U.S.A.I.D. blanket permission to change the
reporting of all indirect costs.”
The
hospital’s construction budget was $50 million. By April of this year,
Bechtel had told the aid agency that because of escalating costs for security
and other problems, the project would actually cost $98 million to complete.
But in an official report to Congress that month, the agency “was
reporting the hospital project cost as $50 million,” the inspector
general wrote in his report.
The rest was
reclassified as overhead, or “indirect costs.” According to a
contracting officer at the agency who was cited in the report, the agency
“did not report these costs so it could stay within the $50 million
authorization.”
“We find
the entire agreement unclear,” the inspector general wrote of the
U.S.A.I.D. request approved by the embassy. “The document states that
hospital project cost increases would be offset by reducing contractor overhead
allocated to the project, but project reports for the period show no effort to
reduce overhead.”
The report said
it suspected that other unreported costs on the hospital could drive the tab
even higher. In another case cited in the report, a power station project in
Musayyib, the direct construction cost cited by the development agency was $6.6
million, while the overhead cost was $27.6 million.
The result is
that the project’s overhead, a figure that normally runs to a maximum of
30 percent, was a stunning 418 percent.
The figures
were even adjusted in the opposite direction when that helped the agency
balance its books, the inspector general found. On an electricity project at
the Baghdad South power station, direct construction costs were reported by the
agency as $164.3 million and indirect or overhead costs as $1.4 million.
That is just
0.8 percent overhead in a country where security costs are often staggering. A
contracting officer told the inspector general that the agency adjusted the
figures “to stay within the authorization for each project.”
The overall
effect, the report said, was a “serious misstatement of hospital project
costs.” The true cost could rise as high as $169.5 million, even after
accounting for at least $30 million pledged for medical equipment by a
charitable organization.
The inspector
general also found that the agency had not reported known schedule delays to
Congress. On March 26, 2006, Bechtel informed the agency that the hospital
project was 273 days behind, the inspector general wrote. But in its April
report to Congress on the status of all projects, “U.S.A.I.D. reported no
problems with the project schedule.”
In a letter
responding to the inspector general’s findings, Joseph A. Saloom, the
newly appointed director of the reconstruction office at the United States
Embassy, said he would take steps to improve the reporting of the costs of
reconstruction projects in Iraq. Mr. Saloom took little exception to the main
findings.
In the letter,
Mr. Saloom said that his office had been given new powers by the American
ambassador in Baghdad, Zalmay Khalilzad, to request clear financing information
on American reconstruction projects. Mr. Saloom wrote that he agreed with the
inspector general’s conclusion that this shift would help “preclude
surprises such as occurred on the Basra hospital project.”
“The U.S.
Mission agrees that accurate monitoring of projects requires allocating
indirect costs in a systematic way that reflects accurately the true indirect
costs attributable to specific activities and projects, such as a Basra
children’s hospital,” Mr. Saloom wrote.